A draft Cleanup Plan has not been submitted to the PADEP. Remedial Investigations must be completed prior to submitting Cleanup Plans and other Act 2 reports that follow Remedial Investigations in the Act 2 process. Upon completion of Remedial Investigation Reports (RIRs) for each of the Areas of Interest, the subsequent Act 2 reports can then be submitted. The Cleanup Plan(s) will be prepared and submitted following the Sitewide Fate & Transport RIR, Sitewide Ecological Risk Assessment Report and any Human Health Risk Assessments completed for the Site. However, remediation (cleanup) activities which were conducted prior to entering the Act 2 program and interim remediation activities currently being conducted are summarized in the RIRs posted to the website.