The rail facilities are located in AOI 5 and AOI 8. Installation of these rail facilities occurred after the property transfer to PES. Therefore, conditions near these lines resulting from their operation would not be part of Evergreen’s investigations. However, the environmental conditions characterized as part of the Act 2 investigations, which included the areas below and around the current rail areas, are included in the Remedial Investigation Reports for AOI 5 and AOI 8. Contaminants associated with past petroleum operations in those areas are summarized in those reports. Evergreen is unable to provide information about the operational conditions related to recent (since 2012) operations of the rails. PES would be better able to respond to those inquiries.