When will the areas be sampled that have not been sampled before because the refineries had been operating and when will that data be made public?

There are some areas under the old process units that weren’t accessible or where it wasn’t safe for us to drill or dig because of ongoing operations. Once those units have been dismantled and the areas are accessible, Evergreen will go out and do additional sampling.  Evergreen has not been provided with the planned schedule of demolition of the unit areas.  However, the sampling will be performed immediately upon clearing of those areas and the data will have to be submitted to the PADEP as part of the Act 2 process after sampling has been conducted.